On February 18 after the house site was marked off, dirt movers came out to scrape soil from a terraced site of a few acres we have on the south side of the property. Hopefully some day soon, we can dig more from that area and create a pond for a water source. They carried the dirt to the site to compact and smoothed it for the compaction test that has to be done before the slab is poured. The compaction test passed at 98% and then they started trenching for the foundation footings on the 22nd. The concrete footings were poured on the 26th and by the 28th, the plumbers were able to rough-in the plumbing and Randy laid out the electrical that needs to be in position before the foundation is poured.